SquareLake Distribution Substation
Client: Florida Power & Light (FPL)
Location: Palm Beach County
Services: Substation construction
Project Type: Brownfield high site conversion
The SquareLake Substation is a designated Florida Power & Light (FPL) Palm Beach County Records facility plat area linked with local distribution and transmission infrastructure. This job consisted of a new 138 kV conversion from distribution to a transmission substation bay, including a 138 kV transmission breaker and associated “G” switches. Additional services included, but were not limited to, high-side bus rework, CCVT, station service transformers replacement, panel installation, cable pulling, steel, metal and structural erection installation.